The Extent of the Problems with the Exchanges is 'enormous', 'Not Just a Glitch' and 'Awful' says Insurance Exec to NYT

From an insurance executive participating in the PPACA Exchanges to the New York Times over the weekend:
... Like many people interviewed for this article, the executive spoke on the condition of anonymity, saying he did not wish to alienate the federal officials with whom he works. “The extent of the problems is pretty enormous. At the end of our calls, people say, ‘It’s awful, just awful.' ” 
Interviews with two dozen contractors, current and former government officials, insurance executives and consumer advocates, as well as an examination of confidential administration documents, point to a series of missteps — financial, technical and managerial — that led to the troubles. ...
Confidential progress reports from the Health and Human Services Department show that senior officials repeatedly expressed doubts that the computer systems for the federal exchange would be ready on time, blaming delayed regulations, a lack of resources and other factors.
Deadline after deadline was missed. The biggest contractor, CGI Federal, was awarded its $94 million contract in December 2011. But the government was so slow in issuing specifications that the firm did not start writing software code until this spring, according to people familiar with the process. As late as the last week of September, officials were still changing features of the Web site, HealthCare.gov, and debating whether consumers should be required to register and create password-protected accounts before they could shop for health plans. 
One highly unusual decision, reached early in the project, proved critical: the Medicare and Medicaid agency assumed the role of project quarterback, responsible for making sure each separately designed database and piece of software worked with the others, instead of assigning that task to a lead contractor. 
Some people intimately involved in the project seriously doubted that the agency had the in-house capability to handle such a mammoth technical task of software engineering while simultaneously supervising 55 contractors. An internal government progress report in September 2011 identified a lack of employees “to manage the multiple activities and contractors happening concurrently” as a “major risk” to the whole project. ...